Distillery Pipework
Tain, Scotland
Overview
JBD Tritec were contracted by a large drinks Manufacturer as the main pipework contractor on site to install all pipework within the new Lighthouse distillery.
Project Specifics
- Supply and installation of 16 pumps.
- Tie-ins between new and existing plant throughout the site for all processes / services
- Over 2800m of process / service pipework installed.
- Service / process lines including:
- Steam and condensate
- Spirit lines
- Clean in place lines
- Compressed air
- Low wines & feints
- Water (hot, cooling etc)
- Caustic
- Installation of main vessels (lauter tun, mash tun, washbacks, spirit recievers etc).
- Installation of all ancillary equipment (pumps, heat exchangers, agitators etc).
- On site commissioning assistance.