Distillery Capacity Increase
Dumbarton, Scotland
Overview
JBD Tritec were contracted by a long standing client for over 30 years to carry out the full mechanical install of there capacity increase plant.
JBD Tritec offered a turnkey solution for the client.
Project Specifics
- Modification to 10no storage vessels.
- Erection of 10no storage vessels and all supporting steelwork.
- Close co-ordination with railtrack to ensure no disruption to the adjacent railway line.
- Design, fabrication and installation of a 50m long pipebridge with associated tank farm gantries, stair towers and walkways.
- Installation of cooling towers.
- All process and service pipework for the new equipment.